if six men can do a peice of work in 2 days, how long will it take one man?

Respuesta :

StraightAstudent100 StraightAstudent100
  • 19-06-2021

Answer: 8 hours

Step-by-step explanation: convert 2 days into hours, 48 hours and divide 48 by 6 to find how long it will take for 1 man

Answer Link

Otras preguntas

Leanne multiplied 8 times 4.3 and got 32.24. Is Leanne correct use an area model to explain your answer
Consider the helix r(t) = ( cos(2t), sin(2t), 2t ), Compute, at t = pi / 6( a. Unit Tangent vector T = ( ___, ___, ___)( b. Unit Normal vector N = ( ___, ___, _
what is the integration of 1/a^2-x^2
What is the name of a solid object traveling through space that strikes Earth’s atmosphere? a,meteor b,meteorite c,meteoroid d,asteroid
If more people try to buy a product because the price has been reduced, what has been increased?
8x-3=11-6x please SHOW ALL STEPS thank you
what is the answer to this question plz help
Which of the following identifies an interest in shared between ancient Greek and Roman texts and the texts of Renaissance artists?
The first Duma was formed in Russia as an elected legislative body - a step toward representation in government. How did this impact Russian government? A.) The
Given the following: CD←→ is the perpendicular bisector of AB¯¯¯¯¯ Point G is the midpoint of AB¯¯¯¯¯ Points E and F lie on CD←→ Identy the pair of line segment