A project activity has an earliest completion time of 5, an activity time of 3, and a latest completion time of 6. What is the slack time for the activity?

Respuesta :

Tundexi
Tundexi Tundexi
  • 17-12-2020

Answer:

1

Explanation:

The Formula for calculating Slack Time is as below:

Slack Time = Latest Completion Time - Earliest Completion time

When Latest Completion Time = 6 ; Earliest Completion time = 5

Slack Time = 6 - 5

Slack Time = 1

Thus,  the slack time for the activity is 1 . The essence of calculating this is to prevent delays in the project completion.

Answer Link

Otras preguntas

what are examples for a rate
1.Grandmother gave Carlos and Tina a new dog last month.   A. predicate nominative
how many pairs of whole numbers have a sum of 40
What material lets electricity flow freely please
In what ways does the federal government step on the rights of the states? Why?
What is 5.6 × 10^−3 yd/year in feet per day?  A.6.813 × 10^−7  ft/day  B.6.132 × 10^−6  ft/day  C.5 × 10^−6  ft/day  D.4.6 × 10^−5  ft/dayPlease explain the ans
Is 85 prime or composite
Last hw for the week. plz helppp
Describe the diversity of the animal kingdom
In what ways does the federal government step on the rights of the states? Why?