If the budget at completion for a project is $200,000 and the cost performance index is .5, what is the estimate at completion

Respuesta :

ayfat23
ayfat23 ayfat23
  • 20-10-2020

Answer:

$400,000

Explanation:

Estimate at completion in finance can be explained as forecast cost of a particular project. It can be estimated by using the expression below

Estimate at completion =[Budget at Completion] /(Cost Performance Index)

From the question, our budget at completion for a project = $200,000

cost performance index is = 0 .5,

Then just input the values we have,

Estimate at completion= 200000/0.5

=$400,000

Therefore, Estimate at completion is

$400,000

Answer Link

Otras preguntas

A ____Always has a numerator of 1
63 is 45%of what number
Find the new amount- Decrease 700 by 49%
How would sediments most likely end up in a sand dune due to natural processes ?
Cliford's constitution of 1922
Why do more people live in eastern africa than northern africa?
Subtract: (-1) - 9 8 10
One way to maintain the integrity of a records management system is to circulate to all employees a list of the many documents the company creates and how they'
A 100-meter sprint is a race using only the straight side of a racetrack. A 400-meter sprint is a race that makes one complete lap around a racetrack. Why are v
Suppose you encounter an unfamiliar word as you're reading. one way to figure out the meaning of this word is to a. survey the section of material. b. use met