2. Why is defining activities a process of project schedule management instead of project scope management

Respuesta :

topeadeniran2 topeadeniran2
  • 20-07-2020

Answer:

Explanation:

Project schedule management is the allocation of timeframe to the task s to be done for a project to be successful while project scope management show the work that needs to be done.

Defining activities is a process of project schedule management, because it simply concentrates on how and when a task will be carried out while in project scope management l, the focus is on the work that will be performed on a project.

Answer Link

Otras preguntas

Quantities or measured properties that are capable of changing values are called
All of the following are strategies to enhance active listening except: A. reflecting on information. B. paraphrasing information. C. repeating informa
How to write an algebraic expression as a verbal expression
what is the mean deviation of 4, 3, 4, 5, 6, 6, 8, 4?
what are two scientific issues that involves ethics
In what order do the steps of the scientific method take place?
ASAP ANSWER PLEASE!!!! I want a new watch, I have to earn the money for it. A. complete sentence B. run-on sentence C. comma splice
The ____ is the body's main artery
Buker corporation bases its predetermined overhead rate on the estimated machine-hours for the upcoming year. data for the upcoming year appear below: estimated
How do you write forty billion,forty eight million