If your company needs to produce 7,800 products by the end of the next 12 weeks, how many products will you need to produce each week to finish on schedule?

A. 680
B. 650
C. 620
D. 580

Respuesta :

MsTeel
MsTeel MsTeel
  • 18-03-2019

B. 650

Divide number of units by number of weeks

7800 units/12 weeks = 650 units per week on average

Answer Link
ardeatley
ardeatley ardeatley
  • 19-03-2019

B. 650

7800 divided among 12 weeks is 650.

Answer Link

Otras preguntas

Brandon is 6 times as old as Cora. In 4 years, Brandon will be only twice as old as Cora will be then. Find Brandon’s age now.
Calculate the number of moles 3.15 g of HNO3 19.3 g of NaCl 21.25 g of NaNO3
In which country did the hutu people practice genocide against the Tutsi was it Rawanda or noHelp Please
What is the climate of ths western region of the us?
What is the climate of ths western region of the us?
If 80 pounds of seed costs $96, what would be the costs of 300 pounds of seeds
How do you respond to con que frecuencia pracaticas deportes?
what was a high wooden fence called in medieval times???
Do you think that Africa was better off a result of European colonization?
find the slope of a line perpendicular to the line whose equation is 3y + 2x = 6