Which of the following will correctly calculate the free slack in an activity? a) Late finish of the activity - Late start of the next activity b) Late start of the activity - Early start of the activity c) Late finish of the predecessor - Early start of the successor d) Minimum early start of all the successors - Early finish of the activity e) Either LS - ES or LF - EF