A construction manager needs 12 workers to complete a building project in 54 days. If the building project needs to be completed in 36 days how many more workers does the construction manager need to complete the project

Respuesta :

Otras preguntas

The government has decided that the free market price of cheese is too low. Farmers complain that the price floor has reduced their total revenue.Is this possib
What is the vertical asymptote for the function f(x) = ln(x + 4) - 2? Be sure to write your answer as an equation for a line.
express each as a single power of 2...2^a X 2^b X 2^c2^a+b X 2^a-b
What is the vertical asymptote for the function f(x) = ln(x + 4) - 2? Be sure to write your answer as an equation for a line.
explain how to do the factor tree for 75
A 700-watt gasoline engine and a 300-watt electric motor both do 3 J of work. Which machine can do the work faster? Explain your answer.
How was the Queen of Hawaii?
A 700-watt gasoline engine and a 300-watt electric motor both do 3 J of work. Which machine can do the work faster? Explain your answer.
in what year did the civil war being?
explain how to do the factor tree for 75